Altona
The building measures for the second berth, to be destined for cruise vessels with a length over 300m, will already start in spring-time 2008. This berth, in total the third one, will be completed in August 2009. The terminal infrastucture will follow during the sommer 2010 and is located at the area Altona. For the berth development, the alignment of the terminal infrastructures, the constructions of the surrounding area and the access road, parking spaces and public areas, the Free and Hanseatic City of Hamburg provides an investment volume of about 12, 5 Mio. Euro.
| Responsible Consortium: | Fischereihafenentwicklungsgesellschaft (FEG), established January 2008 |
| Start of Construction: | Autumn 2008 |
| End of Construction: | Autumn 2009 - berth/ Summer 2010 - terminal |
| Gross Floor Space: | 2.000 m² on one floor |
| Parking Space: | 200 for long time car-parking 100 for short time car-parking 20 bus spaces Taxi row |
| Berth: | One berth (300m) |
| Transport: | Bus stop |

Hamburg Cruise Center II (Altona)Edgar-Engelhard-Kai Total quay length: 326m |
Contact AltonaFEG Fischereihafenentwicklungsgesellschaft mbH Poppenhusenstrasse 2 Tel: (0 40) 4 26 66-6700 |